Uvas Creek Levee Rehabilitation Project

3 Documents in Project

Summary

SCH Number
2018052025
Lead Agency
Santa Clara Valley Water District
Document Title
Uvas Creek Levee Rehabilitation Project
Document Type
NOD - Notice of Determination
Received
Posted
7/17/2018
Present Land Use
open space/park public facility/neighborhood district
Document Description
Project would consist of inboard and outboard side slope reconstruction along approx. 4,200 linear feet of the levee. An additional 350 linear feet of reconstruction would occur to the outboard embankment. The levee side slope reconstruction would first require knowing the existing grasses to reduce the organic content followed by excavation and benching of the levee. Upon completion of the excavation activities, rebuilding the levee would consist of placing the excavated material in compacted layers. Erosion control matting would be embedded within the rebuilt levee slope and covered with additional fill material until as-built grades are achieved. The rebuilt levee surface would be hydroseeded with a native seed to promote the establishment of grasses. Resurfacing of the existing asphalt pedestrian trail and maintenance road atop the levee would be undertaken to repair damage, if any, from construction equipment.

Contact Information

Name
Tim Tidwell
Agency Name
Santa Clara Valley Water District
Contact Types
Lead/Public Agency

Location

Cities
Gilroy
Counties
Santa Clara
Cross Streets
West Luchessa Ave and Princevalle St
Zip
95020
Total Acres
11
State Highways
101, 152
Railways
Caltrain
Waterways
Uvas Creek, Princevalle Drain
Township
11S
Range
4E
Section
7
Base
MD

Notice of Determination

Approving Agency
Santa Clara Valley Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print