Anaheim South Recycled Water Project (Project); Clean Water State Revolving Fund (CWSRF) No. C-06-8147-110
3 Documents in Project
Summary
SCH Number
2016061041
Lead Agency
City of Anaheim
Document Title
Anaheim South Recycled Water Project (Project); Clean Water State Revolving Fund (CWSRF) No. C-06-8147-110
Document Type
NOD - Notice of Determination
Received
Posted
5/3/2017
Present Land Use
Vacant leased for car dealership overflow parking/Pipeline: ROW/Pump station & tank: public Insitutional Uses; Office
Document Description
The project will install the recycled water supply and metering connection, a recycled water pump station with a tank, and distribution pipelines serving the southern area of Anaheim. Near Rampart Street, the project will construct a new turnout facility on the 66-inch diameter Groundwater Replenishment System pipeline. A new recycled water pump station will be located after immediately adjacent to the GWRS connection. An approx. 50,000 gallon recycled water fore bay/storage tank is planned to be constructed with the recycled water pump station to reduce peak flow effects to the GWRS. Total pipeline installation includes 42,300 linear feet; exclusive of Alternative A is an alternative to installation along Orangewood Avenue from I-5 Freeway to Harbor Blvd. Lateral connections will be made at various locations along the distribution system to connect customer meters.
Contact Information
Name
Sahil Pathak
Agency Name
SWRCB
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Anaheim
Counties
Orange
Cross Streets
Orangewood Ave., & Rampart; Anaheim Way & Stanford Ct
Zip
92806
Total Acres
8 mi
Parcel #
city streets; 232-011-19
State Highways
5 freeway
Railways
LOSSAN
Schools
Ponderosa ES
Waterways
Santa Ana River
Township
4S
Range
10W
Section
25
Notice of Determination
Approving Agency
State Water Board
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.