PP16-009 San Jose/Santa Clara Regional Wastewater Facility Cogeneration Project - Boilers and Chillers Replacement

4 Documents in Project

Summary

SCH Number
2014042039
Lead Agency
City of San Jose
Document Title
PP16-009 San Jose/Santa Clara Regional Wastewater Facility Cogeneration Project - Boilers and Chillers Replacement
Document Type
NOD - Notice of Determination
Received
Posted
5/16/2016
Present Land Use
Water Pollution Control Plant / Public / Quasi-Public
Document Description
The project would include the installation of up to 4 natural gas/bio gas fired reciprocating engines ( up to 12.5 MW total for three of the four operating at any one time) at the San Jose/ Santa Clara Regional Wastewater Facility. The proposed engines would meet or exceed Achieved in Practice emissions standards maintained by the Bay Area Air Quality Management District (BAAQMD). The proposed engines would be housed in a new 36,300 sq. ft. (330 feet x 110 feet) Cogeneration Building that would be constructed within the Facility operational boundary near Zanker Road. The Cogeneration Building would be constructed as a high-bay concrete design, with a height similar to the existing Blower General Building. The proposed Cogeneration Building would also include 4 new stacks for air emissions. The stacks would be 24 inches in diameter and would reach approx. 40 feet in height, which is the same height as the existing stack for the adjacent Blower Generation Building.

Contact Information

Name
Harry Freitas
Agency Name
City of San Jose
Contact Types
Lead/Public Agency

Location

Cities
San Jose
Counties
Santa Clara
Cross Streets
700 Los Esteros Rd
Parcel #
015-31-024
Other Location Info
Alviso

Notice of Determination

Approving Agency
City of San Jose
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes