Pier B On-Dock Rail Support Facility Project; Harbor Development Permit No. 07-021
5 Documents in Project
Summary
SCH Number
2009081079
Lead Agency
Port of Long Beach
Document Title
Pier B On-Dock Rail Support Facility Project; Harbor Development Permit No. 07-021
Document Type
NOD - Notice of Determination
Received
Posted
2/1/2018
Present Land Use
Rail and Industrial/IP Zone: Port related industrial uses/land use district no. 12: harbor/airport district
Document Description
Project would reconfigure, expand, and enhance the existing rail support facility located at Pier B in the Port of Long Beach. The Project would result in additional railcar storage and staging capacity, including 36 additional rail tracks for locomotive refueling, railcar repair, and to accommodate the assembly of cargo trains up to 10,000 feet long.
Project would require realignment of Pier B St., closure of an existing grade crossing at 9th Street, and additional realignments and closures of number of local streets to provide a sufficient area for expansion of the rail yard. Utility lines would be newly constructed or relocated into subsurface utility corridors located between tracks. The full build-out of the Project would require removal of existing ramps to and from the Shoemaker Bridge.
Contact Information
Name
Allyson Teramoto
Agency Name
Port of Long Beach
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Long Beach
Counties
Los Angeles
Cross Streets
Pico Ave & I-710
Zip
90802
State Highways
I-710, SR 47
Railways
Alameda Corridor
Waterways
Los Angeles River, Pacific Ocean
Notice of Determination
Approving Agency
City of Long Beach
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.