Orange Grove Power Plant Project, Grading Plan L-15454m Habitat Loss Permit HLP 08-003

3 Documents in Project

Summary

SCH Number
2009049009
Lead Agency
California Energy Commission
Document Title
Orange Grove Power Plant Project, Grading Plan L-15454m Habitat Loss Permit HLP 08-003
Document Type
NOD - Notice of Determination
Received
Posted
5/14/2009
Present Land Use
General Agriculture A-72, Civil Use Type project permitted under zoning A-72
Document Description
The DFG is issuing Streambed Alteration Agreement #1600-2008-0286-R5 to the project applicant, Orange Grove Energy, LP. The applicant proposes to alter the streambed of the San Luis Rey River and 6 unnamed tributaries to the San Luis Rey River, to accommodate construction of the Orange Grove Power Plant Project, a 96 MW electric generating plant designed to serve loads during peak demands. Project activity includes construction of an ~0.3 mile underground electric transmission line that will connect the site to the existing Pala substation, and an ~2.4 mile long, 10 inch natural gas transmission line. The pipeline and underground transmission line (linear facilities) will be installed utilizing "open trench" cut and backfill construction except for 7 streambed locations where horizontal boring will be used to drill underneath the streambeds. The project will utilize either the Horizontal Directiuonal Drilling (HDD) Method of the Jack-and-Bore Method at each of the 7 streambed crossings depending upon specific conditions encountered during construction.

Contact Information

Name
Tamara Spear
Agency Name
Department of Fish and Game
Contact Types
Lead/Public Agency

Location

Counties
San Diego
Cross Streets
Unincorporated area, ~ 2 miles west from community of Pala, CA
Zip
92059
Total Acres
12.5
Parcel #
110-072-26
State Highways
SR-76
Other Location Info
City/Nearest Community: Pala

Notice of Determination

Approving Agency
DFG
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No