- Eastside Road and Westside Road Bridges Replacement Project
- Description
- The proposed Project would replace the existing bridges over Canyon Hollow Creek with new two lane cast-in-place concrete slab bridges. The proposed structures will provide two 12-foot travel lanes, 4 to 8-foot shoulders, and a 6-foot wide sidewalk. The approach roadways will be reconstructed to conform to the new bridges. The Project also includes underground utility relocation, sidewalk extension, storm drain modification, paving, striping, and sign installation. Construction of both bridges will be staged to allow a single lane of alternating traffic, controlled by temporary signals. Most work would occur within the City right of way; however, sliver acquisitions and easements may be required.