SCH Number 2018092013
Project Info
- Title
- Underground Flow Equalization System Project
- Description
- The proposed project consists of a new temporary wastewater holding structure, pump station, odor control equipment room, and associated diversion pipelines. The holding structure is a 5.3 million gallon underground concrete basin that will temporarily hold diluted wastewater flows up to 24 hours upstream from the City's wastewater treatment plant. The temporary holding structure also would provide short-term wastewater storage to facilitate future sewer construction projects and operation and maintenance activities, such as pipeline inspection and cleaning. The project would also include a new emergency diesel generator.
3 documents in project