SCH Number 2018091025


Project Info

Title
Livingston 1, 2, 3 - TCP Removal Treatment System Project
Description
The city plans to make several improvements to increase the city's water system capacity and improve centralized proposed trichloropropane treatment. Specifically, the project will consist of installing new pipeline between existing Wells 8, 9, 13, and 17 and the proposed centralized treatment facilities; new treatment trains to the existing TCP centralized treatment facility; and a new treated water storage tank and booster pump station. Construction is anticipated to start in summer 2019 and will be completed by 2021. Existing water service will not be impacted during construction.
Download CSV New Search

 

2 documents in project

Type Lead/Public Agency Received Title
City of Livingston Livingston 1, 2, 3 - TCP Removal Treatment System Project
City of Livingston Livingston 1, 2, 3 - TCP Removal Treatment System Project