Project Info
- Title
- Anaheim Resort Electric Line Extensions Project
- Description
- Project is the extension of an underground electric line that will connect to existing substation circuit breakers. Approximately 8,000 lf of cable line will be pulled through an existing ductbank, and approximately 11,000 lf will be installed within a new ductbank. The new ductbanks will require a trench generally excavated to a depth of 4-10 ft at a width of approximately 2 ft. Additionally approximately 2,500-3,000 lf of ductbank will be installed on Cerritos Ave and Anaheim Blvd for the future installation of a 69kV line that will be installed under a future project in mid-2017. The areas of ductbank total approximately 4.25 miles. Other project features include install of risers and vaults max vault depth = 10ft x 8ft x 20ft long.
2 documents in project