SCH Number 2013011019
Project Info
- Title
- Foothill Trunk Line Unit 3
- Description
- NOTE: Response to Comment. LADWP proposes to install a 54-inch welded steel pipe as part of the proposed Foothill Trunk Line Unit 3 Project (proposed project). The proposed project would replace and upsize approximately 16,600 linear feet of the existing FTL from northwest of Hubbard Street, where it would connect to the 60-inch PCCP, to just southeast of Terra Bella Street, where it would connect to a 36-inch pipe along Foothill Boulevard and a 30-inch pipe on Terra Bella Street. Furhtermore, the proposed project would minimize dependency on the Sheldon Pump Station and would allow the LADWP to decommission several pipelines, which have a history of leaks, currently servicing the area. The proposed project would be located in the City of Los Angeles in the communities of Sylmar and Pacoima.
3 documents in project