- Title
- Improvement District No. 53 Sewer Project
- Description
- A 33-inch trunk sewer main (including manholes, wet well, tie-ins, asphalt removal, trenching, asphalt replacement, traffic signal loop replacement, traffic striping and marking replacement, survey and monument replacement) will be constructed adjacent to an existing 24-inch sewer line within the roadbeds of Monterey Avenue, Hovley Lane, Portola Avenue, Corporate Way, Avenue 42 and Cook Street, then will be connected to Water Reclamation Plant No. 10. The new sewer line, approximately 3 miles long, would improve sewer service and capacity in the project area.
2 documents in project