Kenzo Winery, Use Permit Major Modification #P19-00396
2 Documents in Project
Summary
SCH Number
2020100530
Lead Agency
Napa County
Document Title
Kenzo Winery, Use Permit Major Modification #P19-00396
Document Type
NOD - Notice of Determination
Received
Posted
12/8/2020
Present Land Use
Winery
Document Description
Approval of a Use Permit Major Modification to an existing 102,000 gallon per year winery to allow the following: ( 1) Increase in maximum annual permitted wine production from 102,000 to 150,000 gallons; (2) Expand the existing 22,470 square foot cave (Type two (2)) to a 68,415 square foot (Type three (3)) cave; (3) Excavation of two (2) new cave portals; (4) Paving an unpaved road for portal access; (5) Deposit of approximately 20,300 cubic yards of cave spoils at a spoils stockpile on land owned by the applicant, 0.9 miles southeast of the project site; (6) Utilize 720 square feet of the cave expansion as a tasting room; (7) Construct 3,350 square feet of a covered crush pad; (8) Construct 820 square feet of an uncovered mechanical yard; and (9) Expand the existing wastewater treatment and disposal systems to handle the increase in winery process wastewater. The project also includes a request for an exception to the Napa County Road and Street Standards (RSS) and the requirement to widen a 500-foot section to 22 feet on Wild Horse Valley Road from Monticello Road to the winery.
Contact Information
Name
Trevor Hawkes
Agency Name
County of Napa
Contact Types
Lead/Public Agency
Phone
Name
Agency Name
Kenzo Estate, Inc
Contact Types
Project Applicant
Location
Coordinates
Counties
Napa
Regions
Countywide, Northern California, Unincorporated
Zip
94558
Total Acres
36.13
Parcel #
033-110-075
State Highways
121
Notice of Determination
Approving Agency
Napa County
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes