Bejarano Cannabis Cultivation Project
2 Documents in Project
Summary
SCH Number
2020090375
Lead Agency
City of Coachella
Document Title
Bejarano Cannabis Cultivation Project
Document Type
NOD - Notice of Determination
Received
Posted
12/8/2020
Present Land Use
GP: Heavy Industrial; Zoning: Wrecking Yard
Document Description
ejarano proposes the development of a cannabis cultivation facility on a 10.01-acre site in the City of Coachella, Riverside County, California. Bejarano, the Applicant, proposes two buildings inclusive of greenhouses and a dedicated Administration and Facility building designed to facilitate the cultivation and processing of medicinal marijuana. the application for the cannabis cultivation facility requires the approval of a Conditional Use Permit (CUP) in the M-W (Wrecking Yard) zone, the zone within which the project is located. the project will construct 2 buildings total. The Headhouse building will be 2-stories, totaling 53,244 square feet (SF) in size, while the Cultivation Building will be 1-story totaling 172,461 SF in size. The total building area will be 225,705 SF. The project includes a 52,131 SF retention basin that will collect runoff from the project site, which will be located directly on the eastern boundary of the site.
Contact Information
Name
Luis Lopez
Agency Name
City of Coachella
Contact Types
Lead/Public Agency
Phone
Email
Name
Agency Name
City of Coachella
Contact Types
Project Applicant
Location
Coordinates
Cities
Coachella
Counties
Riverside
Cross Streets
Harrison Street and Avenue 48
Zip
92236
Total Acres
10.01
Parcel #
603-290-020 & 602-290-21
State Highways
86
Township
5S
Range
8E
Section
32
Base
SBBM
Notice of Determination
Approving Agency
City of Coachella
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No