Portola Road Bridge Replacement Project (Bridge Number 35C0055)

2 Documents in Project

Summary

SCH Number
2020059017
Lead Agency
City of Woodside
Document Title
Portola Road Bridge Replacement Project (Bridge Number 35C0055)
Document Type
NOD - Notice of Determination
Received
Posted
6/23/2020
Document Description
The project involves replacing the Portola Road Bridge over Alambique Creek with an 81.5-foot-long by 30-foot-wide two-span prestressed precast concrete bridge. The bridge would be configured with two 10-foot lanes, a 4-foot, 3-inch shoulder on the eastbound side (southern), an approximately 2-foot wide shoulder on the westbound side (northern), and concrete barriers on both sides.

Contact Information

Name
Jackie Young
Agency Name
Town of Woodside
Contact Types
Lead/Public Agency

Name
Agency Name
Town of Woodside Engineering Department
Contact Types
Project Applicant

Location

Cities
Woodside
Counties
San Mateo

Notice of Determination

Approving Agency
Town of Woodside
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Download CSV New Search Print