Raven Hill Garden
3 Documents in Project
Summary
SCH Number
2020031128
Lead Agency
Lake County
Document Title
Raven Hill Garden
Document Type
NOD - Notice of Determination
Received
Posted
8/6/2020
Present Land Use
RL-Rural Land-Residential Dwelling
Document Description
The +49.5 acre subject site is located at 1020 Junction Plaza, Clearlake, and is known as APN 010-055-45. The 75,360 square feet cultivation area. The project would consist of constructing a six (6) foot chain link fence, placing the security measures/cameras, gravelling the driveway approximately 550 feet in length, and establishing the above ground pots for a two-acre outdoor cannabis cultivation area. The applicant would construct a 5,000 square foot processing facility, 400 square foot storage facility for pesticides/fertilizer; two (2) 5,000 gallon water tanks and three (3) greenhouses. The square footage of each green house is as follows: 9,000 sq. ft.; 14,400 sq. ft., 3,000 sq. ft.
Contact Information
Name
Sateur Ham
Agency Name
Lake County Community Development Department
Contact Types
Lead/Public Agency
Phone
Name
Agency Name
Rebecca G. Hebert
Contact Types
Project Applicant
Location
Cities
Clearlake
Counties
Lake
Regions
Northern California, Unincorporated
Cross Streets
Ogulin Canyon/Junction Plaza
Zip
95422
Total Acres
49.52
Parcel #
010-055-45
State Highways
53
Other Information
1020 Junction Plaza
Notice of Determination
Approving Agency
Lake County Community Development Department-Planning Commission
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes