Streambed Alteration Agreement No. 1600-2020-0010-R2 ("McIntosh" Timber Harvest Plan (THP) 2-19-00144-PLU), Siller Brothers Inc.
Summary
SCH Number
2020020041
Lead Agency
California Department of Forestry and Fire Protection
(CAL FIRE)
Document Title
Streambed Alteration Agreement No. 1600-2020-0010-R2 ("McIntosh" Timber Harvest Plan (THP) 2-19-00144-PLU), Siller Brothers Inc.
Document Type
NOD - Notice of Determination
Received
Posted
2/4/2020
Document Description
The projects are limited to the use.of water drafting sites, the removal of an existing culvert, the removal. of an existing Humboldt crossing, the installation of one culvert, and the construction of multiple temporary bridges and their removal at the completion of use. Further explanation of this work can be referenced in section 26e of the THP 2-19-00144-PLU.
Contact Information
Name
Shelby Thomas
Agency Name
Department of Fish and Wildlife North Central Region
Contact Types
Lead/Public Agency
Phone
Location
Counties
Plumas, Yuba
Township
20N
Range
8E
Section
1-4
Base
MDB&M
Other Location Info
The projects are located within the boundaries of a timber harvesting plan in Plumas and Yuba Counties, within CALWATER watersheds Gold Run, Lewis Flat, Brushy Creek and their connecting tributaries.
Townships: 21N
Range: 8E
Sections: 9, 10, 12, 34, and 35
Notice of Determination
Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
Yes (Timber Harvesting Plan)
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No