Document Title
BMX Relocaton (UP 19-21)
Document Type
NOD - Notice of Determination
Received
Posted
3/16/2020
Document Description
The proposed project would result in the construction of an approximately 224,400 sq ft BMX track pad, the construction of an approximately 1,750 sq ft building for concessions, bathrooms, office, storage and registration, bleacher seating and a 61,600 sq ft parking lot with 147 vehicle parking spaces. A new access road would be extended from Marauder Street, along the northeast comer of the parcel and additional access point via a new tum pocket from Cohasset Road. The BMX track will consist of two separate tracks directly adjacent to one another each with a staging ramp, a series of jumps, berms and a finish area. The building will be approximately 1,700 square feet. The bleacher seating will accommodate 300 spectators and additional viewing areas for up to 1000 spectators. Prepping of the project site would include cutting/grading of the entire site and fill of approximately 200 cubic yards of fill volume of material across the site.

Contact Information

Name
Shannon Costa
Agency Name
City of Chico
Contact Types
Lead/Public Agency

Name
Agency Name
City of Chico
Contact Types
Project Applicant

Location

Cities
Chico
Counties
Butte
Cross Streets
Marauder Street

Notice of Determination

Approving Agency
City of Chico
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes