Bear Creek Culvert Rehabilitation Project

3 Documents in Project

Summary

SCH Number
2019029047
Lead Agency
California Department of Transportation, District 5
Document Title
Bear Creek Culvert Rehabilitation Project
Document Type
NOD - Notice of Determination
Received
Posted
5/31/2019
Document Description
The proposed project will pave the culvert invert (i.e., the lowest part, or floor, of the culvert) with a 6-inch slab of concrete and constructing a fish passage structure to remediate the barrier to fish passage created by stream scour at the culvert outlet. The fish passage structure would be composed of a series of forty weirs (each 26-inches high with a 1-foot-wide by 4-inch-deep low-flow notch). At the culvert outlet, eight pools will be created, each approximately 3-foot by 4-foot in area and will replace the existing concrete apron. An 18-inch walkway will also be constructed along the south culvert wing wall.

Contact Information

Name
Sunny McBride
Agency Name
Caltrans, District 5
Contact Types
Lead/Public Agency

Name
Agency Name
California Department of Transportation, District 5
Contact Types
Project Applicant

Location

Counties
Santa Barbara
Cross Streets
Highway 154 and Paradise Road

Notice of Determination

Approving Agency
Caltrans
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes