36-inch Transmission Main Replacement
2 Documents in Project
Summary
SCH Number
2018091036
Lead Agency
Sweetwater Authority
Document Title
36-inch Transmission Main Replacement
Document Type
NOD - Notice of Determination
Received
Posted
12/13/2018
Present Land Use
public ROW; OS; Park/recreation
Document Description
The project involves the installation of approx 16,500 lf of water transmission main and the abandonment of the existing main within the Sweetwater River valley. The majority of the transmission main would be installed within proximity to the existing alignment, while some portions would be realigned. The project has been designed so that construction activities would remian in previously developed areas to the maximum extent possble. The primary objective of the Project is to replace the ecisting main in order to ensure reliability of the treated water supply to Sweetwater Authority's customers throughout its service area.
Contact Information
Name
Israel Marquez
Agency Name
Sweetwater Authority
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Chula Vista
Counties
San Diego
Cross Streets
Bonita Rd and Willow St
Zip
91902
Total Acres
20
Parcel #
various
State Highways
I-805, Hwy 54 & 125
Schools
Sunnyside ES, etc.
Waterways
Sweetwater River
Base
SB
Other Location Info
Bonita
Notice of Determination
Approving Agency
Sweetwater Authority
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.