Northwest Levee Improvements and Stone Road Seepage Reduction Project
4 Documents in Project
Summary
SCH Number
2018072062
Lead Agency
Bethel Island Municipal Improvement District
(BIMID)
Document Title
Northwest Levee Improvements and Stone Road Seepage Reduction Project
Document Type
NOD - Notice of Determination
Received
Posted
10/18/2018
Present Land Use
general/heavy ag, single fam high-density res, water rec, flood hazard combining dist. overlay
Document Description
BIMID proposes to conduct a project at two different sites. Site 1 - would implement improvements along the waterside and landslide of the Taylor Slough levee on the northwest side of the island west of Bethel Island Road and north of Canal Road between levee stations 0+00 and 130+00. Site 2 would implement measures to reduce seepage along the landslide of the Sand Mound Slough levee on the south side of the island along windsweep Road and Stone Rd between levee stations 340+00 and 450+00.
The project will alleviate or minimize the existing levee deficiencies including steep waterside slopes, active scour, seepage through the levee, and potentially liquefiable material within the levee and foundtion. The project integrates levee improvements and habitat enhancement features and provides export water supply reliability by protecting one of the eight western islands. The project is tenatively scheduled for construction from 2019 to 2021.
Contact Information
Name
Regina Espinoza
Agency Name
Bethel Island Municipal Improvement District
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Counties
Contra Costa
Cross Streets
Canal Rd, Stone Rd, Bethel Island Rd, Windsweep Rd and Gateway Rd
Zip
94511
Total Acres
40
Parcel #
029-040-011
Waterways
Dutch, Sand Mound, Taylor and Piper Sloughs
Township
2N
Range
3E
Section
10
Base
MD
Other Location Info
Bethel Island, Jersey Island
Other Information
Bethel Island in Wetlands Land Grant on Jersey Island, CA
Notice of Determination
Approving Agency
Bethel Island Municipal Improvement District
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.