Document Description
The Project is limited to the construction of a warehouse, parking lot, and two stormwater basins, the extension of John Street to
reach the Project Site, construction of a gravel emergency access road, installation of water and sewer lines, construction of an
associated new sewer pump station, and the diversion of two drainages. The extension of John Street will cross four drainages
and culverts will be installed at each drainage. A gravel low-water crossing will be installed at Ramsey Street Wash. Two
drainages will be redesigned to avoid the warehouse structure.
Contact Information
Name
Charles Land
Agency Name
Department of Fish and Wildlife
Contact Types
Lead/Public Agency
Phone
Name
Agency Name
Banning Industrial LP.
Contact Types
Project Applicant
Location
Cities
Banning
Counties
Riverside
Regions
Southern California
Other Location Info
The project is located at unnamed tributaries to Ramsey Street Wash on the south side of
Interstate Highway 10 (I-10) and one mile east of Hargrave Street within the City of Banning in the County of Riverside, State of
California; Latitude 33.924410 N, Longitude 116.844710 W. Sections 11 and 14, Township 3 South, Range 1 East, U.S.
Geological Survey (USGS) map Cabazon, San Bernardino Meridian.
Notice of Determination
Approving Agency
California Department of Fish and Wildlife
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes