Agreement between the Kern County Water Agency (Agency) and California Department of Water Resources (DWR) for Delivery of San Joaquin River Exchange Contractor

2 Documents in Project

Summary

SCH Number
2017119002
Lead Agency
Kern County
Document Title
Agreement between the Kern County Water Agency (Agency) and California Department of Water Resources (DWR) for Delivery of San Joaquin River Exchange Contractor
Document Type
NOD - Notice of Determination
Received
Posted
11/9/2017
Document Description
Water Authority (Authority) 2017 Central Valley Project (CVP) Water to Rosedale-Rio Bravo Water Storage District (WSD) This NOD replaces the NOE filed by the Agency on Oct. 27, 2017. The Agency is entering into the Agreement with DWR to deliver 2017 CVP water to Rosedale-Rio Bravo WSD. In compliance with the CA Environmental Water Quality Act, the Authority filed the Water Transfer Program for the San Joaquin River Exchange Contractors Water Authority 2014-2038 Final EIR/EIS on Jan 28, 2013. As part of the Authority's Water Transfer Program, U.S. Bureau of Reclamation will make available to the Agency on behalf of its member unit Rosedale-Rio Bravo WSD up to 50,000 acre-feet of the Authority's 2017 CCVP water currently in storage in San Luis Reservoir, for delivery to Rosedale-Rio Bravo WSD.

Contact Information

Name
Stuart Pyle
Agency Name
Kern County
Contact Types
Lead/Public Agency

Location

Counties
Kern

Notice of Determination

Approving Agency
Kern County Water Agency
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes