Environmental Impact Report No. 7257 Fifth Standard Solar Project Complex

3 Documents in Project

Summary

SCH Number
2017091038
Lead Agency
Fresno County
Document Title
Environmental Impact Report No. 7257 Fifth Standard Solar Project Complex
Document Type
NOD - Notice of Determination
Received
Posted
11/10/2020
Present Land Use
Fallow land
Document Description
Environmental Impact Report No. 7257 for the Fifth Standard Solar Project Complex permitted by Conditional Use permits 3562, 3563, and 3564. Which allows the construction, operation, maintenance, and ultimate decommissioning of a 150-megawatt (MW) solar photovoltaic (PV) generation facility, an up to 20-MW solar PV generation facility, and an up to 100-MW energy storage facility and associated infrastructure. The proposed project is located on twelve contiguous parcels, totaling approximately 1,600 acres in unincorporated Fresno County. A new generation-tie (gen-tie) line would be constructed to connect the solar and storage components of the proposed project to Pacific Gas and Electric’s (PG&E’s) adjacent Gates Substation (point of interconnect). The anticipated lifetime of the proposed project would be 35 years and would be decommissioned once operations of the facility cease.

Contact Information

Name
David Randall
Agency Name
County Of Fresno
Contact Types
Lead/Public Agency

Name
Agency Name
RWE Solar Development, LLC
Contact Types
Project Applicant

Location

Counties
Fresno
Cross Streets
west side of State Route 269 (Lassen Avenue), between Gale Avenue and Jayne Avenue
Parcel #
APNs: 075-060-15s, 075-060-52s, 075-070-01s, 075-070-32s, 075-070-33s, 075-070-34s, 075-070-35s,
State Highways
SR 269
Township
20S
Range
17E
Section
27
Base
MDBM

Notice of Determination

Approving Agency
County of fresno
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes