The SCT/LINK Fueling & Maintenance Facility Project and Mitigated Negative Declaration
2 Documents in Project
Summary
SCH Number
2017082068
Lead Agency
City of Galt
Document Title
The SCT/LINK Fueling & Maintenance Facility Project and Mitigated Negative Declaration
Document Type
NOD - Notice of Determination
Received
Posted
10/10/2017
Present Land Use
PLU: Public/Quasi public;Z:Public/Quasi public, low density residential; GP: Varies
Document Description
The city of Galt is proposing to construct a fueling and maintenance facility to serve the transit bus operations for South County Transit on its existing Corporation Yard Annex site. The project includes demolition of existing structures and development of adjacent APN 150-0112-047, requiring a GP amendment and rezoning. The project's proposed on-site improvements include a maintenance building, administrative offices, fueling facility and fuel farm, wash facility, covered parking for transit vehicles, a parking lot, and equipment storage within three Parks Department "yards". Off-site improvements are anticipated to include a new traffic signal and restriping in Elm Ave. at the site's main entrance. The project would be located on a 3.3-acre site at 550 Elm Ave. in the City of Galt, Sacramento County.
Contact Information
Name
Mark Clarkson
Agency Name
City of Galt
Contact Types
Lead/Public Agency
Address
Phone
Location
Coordinates
Cities
Galt
Counties
Sacramento
Cross Streets
Elm Ave, Poplar Ave
Zip
95632
Total Acres
3.3
Parcel #
150-0056-002, -0112-047
State Highways
99
Railways
UPRR
Schools
Mult
Waterways
Mult
Township
5N
Range
6E
Section
27
Notice of Determination
Approving Agency
City of Galt
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
No