MJ ALDEBARAN WATER DIVERSION AND STREAM CROSSINGS (Lake or Streambed Alteration Agreement No. 1600-2019-0193-R1)
16 Documents in Project
Summary
SCH Number
2017042022
Lead Agency
Humboldt County
Document Title
MJ ALDEBARAN WATER DIVERSION AND STREAM CROSSINGS (Lake or Streambed Alteration Agreement No. 1600-2019-0193-R1)
Document Type
NOD - Notice of Determination
Received
Posted
9/19/2019
Document Description
The notification is for three stream crossing upgrades and one surface diversion.
STX-1 is an existing dirt ford on a Class Ill watercourse. The crossing shall be upgraded to a rocked ford per the attached specifications. Upgrading the crossing will require the excavation and temporary displacement of approximately 4 cubic yards of native soil and sandstone, 60 square feet of overall disturbance (15-feet long by 1.5-feet deep by 4-feet wide) and the replacement of approximately 5 to 10 cubic yards of angular rock. The upgrading of this crossing may require the loss of native grasses and forbs.
See NOD for full details.
Contact Information
Name
Cheri Sanville
Agency Name
Department of Fish and Wildlife Northern Region
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Counties
Humboldt
Parcel #
223-061-050
Other Location Info
The project to be completed is located within the Eel River watershed, in the Garberville area, County of Humboldt, State of California.
Notice of Determination
Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No