Santa Felicia Dam Safety Improvement Project EIR
4 Documents in Project
Summary
SCH Number
2017041005
Lead Agency
United Water Conservation District
Document Title
Santa Felicia Dam Safety Improvement Project EIR
Document Type
NOD - Notice of Determination
Received
Posted
2/15/2019
Present Land Use
dam/open space (OS-160 ac)/Open space (10 acre min)
Document Description
The project addresses two primary safety-related components of the Santa Felicia Dam: 1) replacement of the existing outlet works due to the potential for failure under seismic loading conditions and impacts associated with sedimentation near the intake tower; and 2) increasing the conveyance capacity of the existing spillway to sufficiently pass the Inflow Design Flood, which for the Santa Felicia Dam consists of the Probable Maximum Flood of 220000 cubic feet per second. The Replacement of the outlet works would also include installation of a new hydroelectric turbine. The project does not include an increase in the capacity of the reservoir.
Contact Information
Name
Maryam Bral
Agency Name
United Water Conservation District
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Counties
Ventura
Cross Streets
Piru Canyon Rd
Zip
93040
Parcel #
016-0-021-035
Waterways
Lake Piru Reservoir
Other Location Info
Piru
Notice of Determination
Approving Agency
United Water Conservation District
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes