Todd Academy Expansion Project

2 Documents in Project

Summary

SCH Number
2017041001
Lead Agency
Corona-Norco Unified School District
Document Title
Todd Academy Expansion Project
Document Type
NOD - Notice of Determination
Received
Posted
5/22/2017
Present Land Use
school/school/R-3
Document Description
The District is proposing to expand the school by adding relocatable interim buildings and constructing a permanent building on land that is currently a play field. The project also involves demobilization of all interim buildings upon completion of the permanent buildings, and recovering building pads as a playground turf area. District proposes to install 4 relocatable interim buildings to accommodate 125 8th grade students. These interim buildings are to be located along the south-eastern portion of the Project Site along Mayhew Canyon Road. The District proposes to construct a permanent building to accommodate 250 students (the 125 8th graders noted above, plus 125 7th graders currently accommodated in other relocatable interim buildings). The proposed permanent buildings is a two-story academic facility consisting of approx. 25,000 gross sq. ft. (12,500 sq. ft. first floor plan area). The permanent building will contain standard classrooms, physical education locker rooms, and science, art, and band labs. The permanent building is to be located on the south-western portion of the Project Site along Coral Canyon Road. Upon Completion of the permanent building, the District would demobilize the relocatable interim buildings. There would be 11 interim buildings to remove, including the 4 discussed above for the 8th graders, and the remaining 7 that currently house the 7th graders.

Contact Information

Name
Lynne E. Murray
Agency Name
Corona-Norco Unified School District
Contact Types
Lead/Public Agency

Location

Cities
Corona
Counties
Riverside
Cross Streets
Mayhew Canyon Rd and Coral Canyon Rd
Zip
92883
Total Acres
approx
State Highways
only 115
Waterways
various

Notice of Determination

Approving Agency
Corona-Norco Unified School District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes