Haiwee Power Plant Penstock Replacement Project
4 Documents in Project
Summary
SCH Number
2016091018
Lead Agency
City of Los Angeles
Document Title
Haiwee Power Plant Penstock Replacement Project
Document Type
NOD - Notice of Determination
Received
Posted
12/29/2016
Present Land Use
LU and Z: open space (OS-40)
Located on land owned by the City and the Bureau of Land Management.
Document Description
LADWP operates the existing Haiwee Power Plant Penstock for the conveyance of water from the south Haiwee Reservoir to the Haiwee Power Plant as part of the overall LA Aqueduct System. Due to a partial collapse of the penstock in 1984, and decades of corrosion and pitting, normal operation of the penstock does not meet current day design standards. This project would replace approx. 10,000 feet of existing pipe to allow the safe transmission of water from the South Haiwee Reservoir to the Haiwee Power Plant.
Contact Information
Name
Julie Van Wagner
Agency Name
City of Los Angeles
Contact Types
Lead/Public Agency
Phone
Location
Counties
Inyo
Cross Streets
South Haiwee Loop Rd
Zip
93549
Total Acres
120
State Highways
395
Waterways
South Haiwee Reservoir
Other Location Info
South Haiwee Loop Road
Notice of Determination
Approving Agency
LA Dept. of Water and Power
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes