Grove Village [California Endangered Species Act (CESA) Incidental Take Permit No. 2081-2018-045-03 (ITP)]
2 Documents in Project
Summary
SCH Number
2016082054
Lead Agency
City of Santa Rosa
Document Title
Grove Village [California Endangered Species Act (CESA) Incidental Take Permit No. 2081-2018-045-03 (ITP)]
Document Type
NOD - Notice of Determination
Received
Posted
3/29/2019
Document Description
The Project includes the development of 18.09 acres of undeveloped land into a residential development including approximately 136 single-family homes, interior roadways, and a park. Project activities include grubbing and grading of the entire Project Area, trench digging,.-road construction, tree removal, and other activities.
The Project will result in permanent impacts to 18.09 acres of California tiger salamander (Ambystoma californiense) habitat. The Project is expected to result in incidental take of California tiger salamander, which is designated as a threatened species under CESA. The ITP referenced above as issued by CDFW authorizes
incidental take of species listed under CESA that may occur as a result of Project implementation.
Contact Information
Name
Melanie Day
Agency Name
CDFW
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Santa Rosa
Counties
Sonoma
Other Location Info
The Project is located immediately east of Stony Point Road and approximately 0.1 miles north of Bellevue Avenue, bound to the north by a high-density residential development and to the east by Elsie Allen High School.
The project footprint is 18.09 acres.
Notice of Determination
Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes