Bank Stabilization Project in the De Anza Channel at the Closed Pedley Landfill
Summary
SCH Number
2016058183
Public Agency
California Department of Fish and Wildlife, Region 6
(CDFW)
Document Title
Bank Stabilization Project in the De Anza Channel at the Closed Pedley Landfill
Document Type
NOE - Notice of Exemption
Received
Posted
5/16/2016
Document Description
The Project site is a landfill that has not operated since approximately 1958. In November 2015, a small portion of the closed Pedley Landfill suffered erosion damage. The affected area is located in the northwest corner of the landfill, adjacent to the De Anza Channel.
The proposed project includes excavation of exposed landfill material and slope armoring with a revetment system- articulated concrete blocks (ACB). The ACB will be covered with engineered fill, allowing for future re-vegetation of the site. Project construction will occur above the waterline and appropriate best management practices (BMPs_, in addition to an onsite biological monitor, will ensure that any Project related impacts, while not anticipated, remain negligible. The project will cure the recent erosion conditions, as well as provide critical protection to the De Anza Channel, Santa Ana River, and surrounding environment during future rain events.
Contact Information
Name
Eddy Konno
Agency Name
California Department of Fish and Wildlife, Region 6
Contact Types
Lead/Public Agency
Phone
Location
Cities
Riverside
Counties
Riverside
Parcel #
163-300-008,163-300-009,163-300-010
Notice of Exemption
Exempt Status
Categorical Exemption
Type, Section or Code
S:15301,15302,15308 C:1,2,8
Reasons for Exemption
The Project is both statutorily and categorically exempt from the provisions of CEQA specifically by the State CEQA Guidelines as identified below. The project will not result in any specific or general exceptions to the use of categorical exemptions as detailed under State CEQA Guidelines Section 15300.2. The Project will not cause any impacts to scenic resources or unique sensitive biological environments and instead will improve the environment once the Project is completed. No unusual circumstances or potential cumulative impacts would occur that may reasonably create an environmental impact and the Project site is not included on any list pursuant to Government Code Section 65962.5