Chevron Eureka Terminal Seismic Retrofit (California Endangered Species Act Incidental Take Permit No. 2081-2016-034*01 (ITP)

3 Documents in Project

Summary

SCH Number
2016052046
Lead Agency
Humboldt Bay Harbor
Document Title
Chevron Eureka Terminal Seismic Retrofit (California Endangered Species Act Incidental Take Permit No. 2081-2016-034*01 (ITP)
Document Type
NOD - Notice of Determination
Received
Posted
9/9/2016
Present Land Use
APN 007-071-013-WD - Development Water & APN 007-071-013 CDI - Coastal Dependent Industrial
Document Description
This proposed project involves conducting a seismic retrofit of the Chevron fuel dock to bring the fuel pipe way support structure into compliance with the CA Building Code. Project activities include removal of creosote piles, installation of steel piles using vibratory and impact hammering, and removal and replacement of part of the existing redwood deck. Project is expected to result in incidental take of longfin smelt (Spirinchus thaleichthys) which is designated as a threatened species under the CESA. The ITP referenced above as issued by CDFW authorizes incidental take of species listed under CESA that may occur as a result of Project implementation.

Contact Information

Name
Craig Shuman
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Cities
Eureka
Counties
Humboldt
Cross Streets
3400 Christie St
Zip
95501
Parcel #
007-071-13, -08
State Highways
101
Waterways
Humboldt Bay, Elk River
Township
5N
Range
1W
Section
33
Base
HB&M

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes