Vaughn Water Company New Municipal Well
2 Documents in Project
Summary
SCH Number
2016042070
Lead Agency
State Water Resources Control Board
Document Title
Vaughn Water Company New Municipal Well
Document Type
NOD - Notice of Determination
Received
Posted
7/27/2016
Present Land Use
Kern County Land Zoning A, Exclusive Ag
Document Description
SWRCB as the lead agency willbe issuing a water supply permit. The proposed project involves drilling and equipping a new municipal water well facility for Vaughn Water Company (VWC) and connecting it to the existing VWC distribution system. The well will obtain groundwater from an approx. depth of 700 foot to 1,200 foot. If hydrogen sulfide is encountered, well head treatment will be installed in the form of ozonation to remove the taste and odor problem. The well will be equipped with a turbine pump and will have a 400-hp electric motor. The pump will lift 2,500 gallons per minute into a 60,000 gallon stainless steel bolted contact tank. The well will be metered and regulated by a flow control valve. The water will then pass through 12-inch and 8-inch stainless steel venturi injectors installed in parallel. In between the well and tank, ozone will be injected into the flow stream. The pressure drop across the venturi injectors will create a suction that draws in the ozone. The ozone will be created by a 70 pounds/day ozone generator manufactured by Ozonia. The ozone generator will be supplied cooling water and dry air and utilize air and electricity to convert oxygen to ozone. All ozone piping will be stainless steel. The process piping, electrical equipment, ozone generator, air compressor, and air dryer will be installed in an air conditioned metal building with an ozone analyzer to detect any ozone leaks. A stainless steel 30 foot wide by 12 foot high bolted tank will be constructed. Water will be conveyed to the distribution system along Hageman Road (approx. 1,300 feet north of the site) to Wegis Avenue and along Winfield Avenue to Wegis Avenue (approx. 2,600 feet east of the site) by three horizontal centrifugal split-case booster pumps, installed discharge piping and appurtenances, a constructed 3,000 gallon hydropneumatic vessel, and installed 12-inch C900 PVC underground piping. The site will include an 18-inch deep retention basin for on-site drainage, an electrical main line extension by PG&E, and site lighting. The site will be enclosed by a 6-foot high chain-link fence with privacy slates and trees planted around the perimeter of the facility to be aesthetically appealing.
Contact Information
Name
Cindy Forbes
Agency Name
State Water Resources Control Board
Contact Types
Lead/Public Agency
Phone
Location
Cities
Bakersfield
Counties
Kern
Cross Streets
vicinity of Nord Rd and Hagemen Rd
Township
29S
Range
26E
Section
21
Notice of Determination
Approving Agency
State WAter Board
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes