San Elijo Water Reclamation Facility Upgrades

3 Documents in Project

Summary

SCH Number
2016021055
Lead Agency
San Elijo Joint Powers Authority
Document Title
San Elijo Water Reclamation Facility Upgrades
Document Type
NOD - Notice of Determination
Received
Posted
5/26/2016
Present Land Use
Public/Semi-Public
Document Description
SEJPA proposes several SEWRF upgrades, rehabilitations, and replacements, including: administration and operations buildings and seismic upgrades; site improvements and security; preliminary treatment upgrades; electrical upgrades; dewatering upgrades; digester improvements; aeration and return upgrades; dissolved air flotation upgrades and co-thickening; supervisory control and data acquisition system installation; and installation of solar fields. A new administration building would be constructed at the southern end of the project site, near the SEWRF entrance off Manchester Avenue.

Contact Information

Name
Mike Konicke
Agency Name
San Elijo Joint Powers Authority
Contact Types
Lead/Public Agency

Location

Cities
Encinitas
Counties
San Diego
Cross Streets
2695 Manchester Avenue
Zip
92007
Parcel #
2610101302
State Highways
I-5
Railways
NCTD
Schools
Cardiff Elem.
Waterways
San Elijo Lagoon, Pacific Ocean
Other Location Info
Cardiff by the Sea

Notice of Determination

Approving Agency
San Elijo Joint Powers Authority
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes