Palo Alto Regional Water Quality Control Plant Sludge Dewatering and Loadout Facility (Project); Clean Water State Revolving Fund (CWSRF) No. C-06-8190
3 Documents in Project
Summary
SCH Number
2015122033
Lead Agency
City of Palo Alto
Document Title
Palo Alto Regional Water Quality Control Plant Sludge Dewatering and Loadout Facility (Project); Clean Water State Revolving Fund (CWSRF) No. C-06-8190
Document Type
NOD - Notice of Determination
Received
Posted
4/12/2017
Present Land Use
Public Facilities, PF (D); Major Institution/Special Facilities
Document Description
The City is taking a proactive action to address the Palo Alto Regional Water Quality Control Plant's aging solids waste handling infrastructure, to comply with changing and uncertain regulations affecting biosolids, and to respond to the community goals to increase the beneficial use of recovered organic resources city-wide. The proposed project includes the construction of a new building to accommodate the installation of four belt filter presses. The Project also includes mechanisms to convey the resulting cake from the belt filter presses to three storage bins, and to load the cake from the bins into trucks. In addition to the dewatering and truck loadout facility itself, a standby diesel engine generator will be installed to provide backup.
Contact Information
Name
Sahil Pathak
Agency Name
SWRCB
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Palo Alto
Counties
Santa Clara
Cross Streets
Embarcadero Road and Embarcadero Way
Zip
94303
Total Acres
0.48
Parcel #
008-03-029
Airports
Palo Alto Airport
Waterways
Palo Alto Baylands, SF Bay
Notice of Determination
Approving Agency
State Water Board
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
N/A