Sheldon Road/Bradshaw Road Intersection Improvement Project (PTO137)
4 Documents in Project
Summary
SCH Number
2015122013
Lead Agency
City of Elk Grove
Document Title
Sheldon Road/Bradshaw Road Intersection Improvement Project (PTO137)
Document Type
NOD - Notice of Determination
Received
Posted
3/14/2016
Present Land Use
Land Use- Low Density residential and agricultural. General Plan - Arterial Intersection
Document Description
The Sheldon/Bradshaw Road intersections is currently a stop sign-controlled intersection located in the Rural Sheldon Area in the City of Elk Grove. Laguna Creek 100-year flows currently overtop the existing bridge at the Sheldon Road/Bradshaw Road intersection. The project proposes to improve the Sheldon Road/Bradshaw Road intersection by replacing the intersection/bridge structure with either box culverts or single span slab bridge. The bridge replacement will plan for partial future widening of Bradshaw Road and Sheldon Road although it will not accommodate the ultimate planned width of four lanes on Sheldon Road. The project will provide operational improvements by reconstructing the bridge and intersection to current standards, and relocate existing utilities in conflict with planned improvements.
Contact Information
Name
Jessica Jordan
Agency Name
City of Elk Grove
Contact Types
Lead/Public Agency
Phone
Location
Cities
Elk Grove
Counties
Sacramento
Cross Streets
Sheldon Road and Bradshaw Road
Zip
95624
Parcel #
Various
Notice of Determination
Approving Agency
City of Elk Grove
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No