Mission Springs Water District Well 33 Solar Photovoltaic Electric Generating System Project

2 Documents in Project

Summary

SCH Number
2015111072
Lead Agency
Mission Springs Water District
Document Title
Mission Springs Water District Well 33 Solar Photovoltaic Electric Generating System Project
Document Type
NOD - Notice of Determination
Received
Posted
2/22/2016
Present Land Use
Open Space (except for Well 33 facility site) / Rural Residential 0-0.4 units per acre / Rural Residential.
Document Description
Development of the proposed well 33 site solar facility (Solar Photovoltaic: Electric Generating System Project) will consist of clearing and grubbing of vegetation from this existing highly disturbed open area; selected surface grading will occur on the approximate 6.5 acre area to support the future solar panels and support equipment; and installation of the solar panels and support equipment as described in more detail in the following text. The District is working with a commercial vendor, SunPower, to install the proposed solar project. The specific layout of this facility may be modified in the future as actual development occurs, but the proposed project will remain within the footprint and this whole facility site will be ultimately utilized. The District will provide minimal, downward facing, security lighting for the solar field.

Contact Information

Name
Danny Friend
Agency Name
Mission Springs Water District
Contact Types
Lead/Public Agency

Location

Cities
Desert Hot Springs
Counties
Riverside
Cross Streets
unpaved segment of Little Morongo Road
Total Acres
6.5
State Highways
I-10
Township
3S
Range
4E
Section
14
Base
SBBM

Notice of Determination

Approving Agency
Mission Springs Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A