Kuhlman Water Diversion and Stream Crossing Project (Lake or Streambed Alteration Agreement No. 1600-2018-0830-R1)

549 Documents in Project

Summary

SCH Number
2015102005
Lead Agency
Humboldt County
Document Title
Kuhlman Water Diversion and Stream Crossing Project (Lake or Streambed Alteration Agreement No. 1600-2018-0830-R1)
Document Type
NOD - Notice of Determination
Received
Posted
5/21/2020
Document Description
The project is limited to 7 encroachments (Table 1). One (1) encroachment is for water diversion from unnamed tributaries to Redwood Creek. Water is diverted for domestic use. Work for the water diversion will include use and maintenance of the water diversion infrastructure. Six (6) proposed encroachments include upgrading failing and undersized stream crossings and ditch relief culverts. Work for these encroachments will include excavation, removal of the failing crossings, replacement with new properly sized crossings, backfilling and compaction of fill, and rock armoring as necessary to minimize erosion.

Contact Information

Name
Nicholas Simpson
Agency Name
Department of Fish and Wildlife
Contact Types
Lead/Public Agency

Name
Agency Name
Humboldt County
Contact Types
Project Applicant

Location

Counties
Humboldt
Other Location Info
The project to be completed is located within the Redwood Creek watershed, approximately 12 miles east of the town of Blue Lake, County of Humboldt, State of California. The project is located in Section 25, T6N, R3E, Humboldt Base and Meridian; in the Maple Creek U.S. Geological Survey 7.5-minute quadrangle; Assessor's Parcel Number 316-172-016.

Notice of Determination

Approving Agency
Department of Fish and Wildlife
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Download CSV New Search Print