San Quentin State Prison Boiler Building Project
2 Documents in Project
Summary
SCH Number
2015032016
Lead Agency
California Department of Corrections and Rehabilitation
(CDCR)
Document Title
San Quentin State Prison Boiler Building Project
Document Type
NOD - Notice of Determination
Received
Posted
4/20/2015
Present Land Use
GPLUD: Public Facilities
Z: Light Agriculture use (A-2:B-2)
Document Description
The project includes demolition of some on-site facilities and construction of a new boiler building and associated facilities, all within the fenced perimeter of San Quentin State Prison (SQSP). The project would bring the boilers at SQSP into compliance with Bay Area Air Quality Management District emissions regulations. All construction would be consistent in character, design, and height with other existing buildings. No high-mast lighting would be installed. The project does not include any new beds and would not increase inmate capacity. No new employees would be hired as part of the project.
Contact Information
Name
Nancy MacKenzie
Agency Name
California Department of Corrections and Rehabilitation
Contact Types
Lead/Public Agency
Phone
Location
Cities
Larkspur, San Rafael
Counties
Marin
Cross Streets
Main Street, Sir Francis Drake Blvd
Zip
94964
Total Acres
1.03
State Highways
I-580, US Hwy 101
Waterways
San Francisco Bay, Corte Madera Creek
Township
1N
Range
6W
Other Location Info
San Quentin Village
Notice of Determination
Approving Agency
California Department of Corrections and Rehabilitation
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.