McCandless Drive Elementary School Project
5 Documents in Project
Summary
SCH Number
2015011051
Lead Agency
Milpitas Unified School District
Document Title
McCandless Drive Elementary School Project
Document Type
NOD - Notice of Determination
Received
Posted
1/29/2016
Present Land Use
Land Use: vacant / Zone: Park and Open Space (POS). Transit Oriented Dedvelopment (TOD) overlay / GP:POS
Document Description
The MUSD is proposing to acquire land on and in the vicinity of McCandless Drive in the City of Milpitas, Santa Clara County, to develop and operate a new TK-6 elementary school capable of accommodating 800 students and 50 faculty and staff. The project is intended to alleviate increases in the MUSD's existing and projected student enrollment, and is planned to be operational in time for the 2018/2019 school year. The project would involve property acquisition, site remediation, school construction and operation, McCandless Drive improvements (e.g., lane extensions), on- and off-site utility improvements, and joint-use of property for school-related and City park purposes.
Contact Information
Name
Cary Matsuoka
Agency Name
Milpitas Unified School District
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Milpitas
Counties
Santa Clara
Cross Streets
Montague Expressway, Great Mall Parkway, Houret Court, Houret Drive, De Long Lane
Zip
95035
Total Acres
10
Parcel #
08641-009, -016/17,-023 to 030, -35/6
State Highways
237, 680, 880
Railways
Union Pacific, BART
Schools
Zanker, Brkside, Randall
Waterways
Penitencia Creek, Coyote Creek
Township
6S
Range
1E
Section
12
Notice of Determination
Approving Agency
Milpitas Unified School District
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.