Remedial Action Plan for LAborde Canyon (Lockheed Martin Beaumont Site 2)
4 Documents in Project
Summary
SCH Number
2014101060
Lead Agency
Department of Toxic Substances Control
Document Title
Remedial Action Plan for LAborde Canyon (Lockheed Martin Beaumont Site 2)
Document Type
NOD - Notice of Determination
Received
Posted
11/4/2016
Present Land Use
Site is currently vacant. Zoning is Manufacturing (Heavy 7 Medium); GP designation is Rural Mountainous & Open Space
Document Description
The proposed project is to clean up the Laborde Canyon (Site), also known as Lockheed Martin Beaumont Site 2, located in unincorporated Riverside County, California. The proposed cleanup includes remediation of contaminated soil and groundwater in five areas where previous site operations were conducted. The proposed remedy is the subject of a Remedial Action Plan (RAP), currently under preparation by DTSC, and includes; groundwater plume containment at the southern boundary of the Site, limited removal and either on-site or off-site treatment of shallow soil in two locations, pilot test and possible groundwater treatment, and institutional controls that would restrict future land use at the site.
Contact Information
Name
Daniel Zogaib
Agency Name
Department of Toxic Substances Control
Contact Types
Lead/Public Agency
Phone
Location
Cities
Beaumont
Counties
Riverside
Cross Streets
Jack Rabbit Trail and State Route 60
Zip
92223
Total Acres
2,668
Parcel #
421-080-001, 421-190-001
State Highways
State Route 60
Notice of Determination
Approving Agency
DTSC
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes