Jalama Road/Salsipuedes Creek Bridge 51C-013 Replacement, County Project Number 863018

2 Documents in Project

Summary

SCH Number
2014011082
Lead Agency
Santa Barbara County
Document Title
Jalama Road/Salsipuedes Creek Bridge 51C-013 Replacement, County Project Number 863018
Document Type
NOD - Notice of Determination
Received
Posted
3/27/2015
Present Land Use
The surrounding area is zoned 100 AG and AG-II-100
Document Description
CDFW is intending to execute a Lake and Streambed Alteration Agreement pursuant to Section 1602 of the Fish and Game Code (# 1600-2014-0053-R5) to the Project applicant, Morgan Jones of the County of Santa Barbara. The Project proposes to strengthen the existing bridge and widen it by 7 feet. The existing bridge is a single span steel plate girder structure with a reinforced concrete deck supported by reinforced concrete abutments and driven "H" pile foundations. This project involves tying two steel plate girders with cross bracing to the existing girder and extending the steel floor beams and reinforced concrete deck slab. The abutments will be supported on 24-inch case-in-drilled hole piles. Jalama Road will be widened by 7 feet to accommodate the width of the bridge. The work will be done on the north side of the existing bridge, and not over the pool that contains southwestern pond turtle (Emys marmorata pallida).

Contact Information

Name
Natasha Lohmus
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Cities
Lompoc
Counties
Santa Barbara
Cross Streets
Jalama Road and State Hwy 1
Zip
93436
Total Acres
<1
Parcel #
County Owned Right of Way
State Highways
1
Waterways
Salisipuedes Creek

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No