Telegraph Creek Barrier Removal and Channel Restoration Project

2 Documents in Project

Summary

SCH Number
2013092030
Lead Agency
Resort Improvement District 1
Document Title
Telegraph Creek Barrier Removal and Channel Restoration Project
Document Type
NOD - Notice of Determination
Received
Posted
11/8/2013
Present Land Use
Natural Resources, Residential Low Density, Conservation Recreation Areas
Document Description
Project consists of the partial demolition of the existing raw water intake structure, the replacement of the barrier culverts through Telegraph Creek Road with a 20-foot span bottomless arch, and channel restoration through the project reach. Demolition of the raw water intake structure includes removing portions of the dam, the infiltration plumbing upstream of the dam, and the stored sediment behind the dam. In addition, the existing wet well will be modified for continued use. The construction reach is limited to approximately 340 feet, bound by the upper and lower fish exclusion fences, and includes the dam, the dam reservoir, and the Telegraph Creek Road stream crossing.

Contact Information

Name
Philip Young
Agency Name
Resort Improvement District #1
Contact Types
Lead/Public Agency

Location

Counties
Humboldt
Cross Streets
Telegraph Creek Road
Zip
95589
Parcel #
109-011-001 and -003
State Highways
No
Railways
No
Airports
Shelter Cove airstrip
Schools
No
Waterways
Telegraph Creek
Township
5S
Range
1E
Section
10
Base
HB&M
Other Location Info
Shelter Cove

Notice of Determination

Approving Agency
Resort Improvement District #1
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.