Laguna Niguel to San Juan Capistrano Passing Siding Project (Lake or Streambed Alteration Agreement No. 1600-2016-0165-R5)

5 Documents in Project

Summary

SCH Number
2013091008
Lead Agency
Orange County Transportation Authority
Document Title
Laguna Niguel to San Juan Capistrano Passing Siding Project (Lake or Streambed Alteration Agreement No. 1600-2016-0165-R5)
Document Type
NOD - Notice of Determination
Received
Posted
11/21/2016
Present Land Use
commercial, parkland, agriculture, transportation/Agri-bus, community park, open space, planned community, single-family
Document Description
Project is limited to those activities described in Permittees Notification of Lake or Streambed Alteration and includes: the addition of passing siding railroad track adjacent to the low flow channel of Oso Creek, relocation of an existing spur track, construction of retaining walls, relocation of existing powerpoles, fiber optic cables, water, and sewer lines; extension of casings for gas, water, and sewer lines, culvert extensions, and addition of railroad bridge or box culvert.

Contact Information

Name
Jennifer Edwards
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Cities
Laguna Niguel, San Juan Capistrano
Counties
Orange
Cross Streets
Camino Capistrano and SR 73
Zip
92675
Total Acres
3.2
State Highways
I-5
Railways
Metrolink Lossan Corridor
Schools
Capistrano Valley HS
Waterways
Oso Creek and Trabuco Creek
Township
7S
Range
8W
Section
25
Base
SBB&M

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.