Incidental Take Permit No. 2081-2018-052-01, Mercer Fraser Commercial Gravel Operation
4 Documents in Project
Summary
SCH Number
2013072066
Lead Agency
Humboldt County
Document Title
Incidental Take Permit No. 2081-2018-052-01, Mercer Fraser Commercial Gravel Operation
Document Type
NOD - Notice of Determination
Received
Posted
9/24/2018
Present Land Use
River bar/ Ag. Exclusive, Natural Resources/ Agriculture Exclusive
Document Description
The project inludes vehicle and heavy equipment use within the riparian corridor and bank full channel of the Mad, Lower Eel, Van Duzen, and Trinity rivers, excavation of aggregate from exposed bar surfaces, excavation of aggregate from deposits adjacent to the low-flow summer stream channel, isolated water bodies, and secondary channels. Access to extraction site amy require the placement and removal of temporary crossings. Excavation may also occur on high floodplain areas and in areas adjacent to riparian vegetation. The annual work period occurs between June 1 and October 15, with the exception of temporary crossings, which are restricted to the work period of June 30 and October 15. Pre-extraction monitoring and planning activities begin as early as April 1 and may extend through July. Post-extraction monitoring and habitat surveys may extend through the month of November. Pre-extraction planning activities may involve travel to survey areas by passenger vehicle on existing haul roads and across exposed gravel bars of the Mad, Eel, Van Duzen river channels. Equipment used for excavation activities include rubber-tired loaders, tracked bulldozers, belly-scrapers, tracked excavators, large off-road haul trucks, belly dumps, dump trucks, personal vehicles, and quad runners.
Contact Information
Name
Jennifer Olson
Agency Name
CDFW Northern Region
Contact Types
Lead/Public Agency
Phone
Location
Cities
Fortuna
Counties
Humboldt
Cross Streets
Dinsmore Drive and US Hwy 101
Zip
95540
Parcel #
multiple
State Highways
Hwy 101
Railways
Eureka Southern
Schools
Union High
Waterways
Mad River, Eel River, Van Duzen River, Trinity River
Township
3N
Range
1E
Section
34
Base
HB&M
Notice of Determination
Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.