Rio Linda Boulevard Bridge Replacement Project

7 Documents in Project

Summary

SCH Number
2013062024
Lead Agency
City of Sacramento
Document Title
Rio Linda Boulevard Bridge Replacement Project
Document Type
NOD - Notice of Determination
Received
Posted
10/30/2013
Present Land Use
Suburban, Suburban Neighborhood Low, and Parks and Recreation
Document Description
The project consists of replacing the Rio Linda; realigning Magpie Creek to allow for realigning Main Ave within the City's existing right-of-way to intersect with Rio Linda Blvd at a right angle; constructing left and right turn lanes from Main Ave onto Rio Linda Blvd, new crosswalks, access to the Northern Sacramento Bike Trail, and installation of a traffic signal. One through lane will be provided in each direction along Rio Linda Blvd with an additional receiving lane to accommodate the required dual left turns from Main Ave. The Rio Linda Blvd roadway profile will be raised slightly to provide the required hydraulic clearance. The Rio Linda Blvd Bridge replacement will require the overhead utilities along Main Ave and Rio Linda Blvd to be relocated.

Contact Information

Name
Scott Johnson
Agency Name
City of Sacramento
Contact Types
Lead/Public Agency

Location

Cities
Sacramento
Counties
Sacramento
Cross Streets
Rio Linda Blvd and Main Ave
Zip
95838
Total Acres
5
Parcel #
23700400560, 2260240016
Waterways
Magpie Creek
Township
9N
Range
5E
Section
10/11

Notice of Determination

Approving Agency
City of Sacramento
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes