Document Description
The Project to relocate Phillips 66 Line 200 will relocate a portion of the line from the west side of the California Aqueduct to the east side. The new line will cross both Quinto Creek and an Unnamed Creek. At each location an area of approximately 23 feet by 40 feet will be excavated to a maximum depth of 6 feet. A 16-inch steel oil pipe line will be laid into the open trench and then will be backfilled with approximately 508 cubic yards of the excavated native fill. The areas will then be compacted and restored to pre-construction conditions. All work within the stream will occur during naturally dry conditions. No trees will be removed.

Contact Information

Name
Sarah Paulson
Agency Name
California Department of Fish and Wildlife
Contact Types
Lead/Public Agency

Location

Cities
Gustine
Counties
Merced
Cross Streets
Butts Road and CA Aqueduct (MP62.26 to MP 64.46)
Total Acres
29
Parcel #
various
State Highways
I-5

Notice of Determination

Approving Agency
California Departmetn of Fish and Wildlife
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A