Basin No. 2 Inlet/Turn-out Structure Project
2 Documents in Project
Summary
SCH Number
2013021060
Lead Agency
Water Replenishment of Southern California
Document Title
Basin No. 2 Inlet/Turn-out Structure Project
Document Type
NOD - Notice of Determination
Received
Posted
5/3/2013
Present Land Use
P-F
Document Description
The purpose of the Basin No. 2 Inlet/Turn-out Structure Project (proposed project) is to increase the operational flexibility of the San Gabriel Coastal Spreading Grounds (SGCSG) and enhance the ability to recharge more recycled water. The proposed project consists of one or two reinforced concrete turn-out structures with one being a connection to the existing recycled water pipeline (RWP) and proposed to be constructed on the existing RWP. As part of the proposed project, the Water Replenishment District of Southern California (WRD) may need to conduct rehabilitation of the existing RWP that is located under the access road between the proposed turn-out structures and an existing turn-out structure.
Contact Information
Name
Jim McDavid
Agency Name
Water Replenishment of Southern California
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Pico Rivera
Counties
Los Angeles
Cross Streets
San Gabriel River between Whittier Blvd and Washington Blvd
Total Acres
4.84
Parcel #
6379-001-905
State Highways
I-605
Railways
UPRR
Airports
No
Waterways
San Gabriel River, San Gabriel Spreading Grounds
Township
2S
Range
11W
Section
19
Notice of Determination
Approving Agency
Water Replenishment District of Southern California
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes