001B Turn-out Structure Project
2 Documents in Project
Summary
SCH Number
2013021059
Lead Agency
Water Replenishment of Southern California
Document Title
001B Turn-out Structure Project
Document Type
NOD - Notice of Determination
Received
Posted
5/3/2013
Present Land Use
GPLU: P-F "Public/Quasi Public Facility"; Z: P-F
Document Description
The 001B Turn-out Structure Project (proposed project) consists of a reinforce concrete turn-out structure with a connection to the existing recycled water pipeline (RWP). The concrete turn-out structure may be equipped with values or slide gates for diverting recycled water from the RWP into through a discharge pipeline into the permeable area of the San Gabriel River (SGR) for recharge. The discharge pipeline would extend through the levee and discharge at the surface level of the channel of the SGR. A concrete apron and riprap would be constructed to prevent erosion of the channel bottom.
Contact Information
Name
Jim McDavid
Agency Name
Water Replenishment of Southern California
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Pico Rivera
Counties
Los Angeles
Cross Streets
San Gabriel River between Washington Blvd and Slauson Ave
Total Acres
2.7
Parcel #
6383-039-901
State Highways
I-605
Railways
BNSF/Metrolink
Airports
No
Waterways
San Gabriel River
Township
2S
Range
12W
Section
25
Notice of Determination
Approving Agency
Water Replenishment District of Southern California
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.