Peninsula Corridor Electrification Project
10 Documents in Project
Summary
SCH Number
2013012079
Lead Agency
Peninsula Corridor Joint Powers Board
Document Title
Peninsula Corridor Electrification Project
Document Type
NOD - Notice of Determination
Received
Posted
12/12/2016
Document Description
The proposed project involves the electrification of the Caltrain Corridor from San Francisco's 4th and King Caltrain Station to approx. the Tamien Caltrain Station.
Contact Information
Name
Stacie Cocke
Agency Name
CA Transportation Commission
Contact Types
Lead/Public Agency
Phone
Location
Cities
San Jose
Counties
Santa Clara
Railways
Caltrain
Notice of Determination
Approving Agency
CA Transportation Commission
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.