Administration Drive Sewer Improvements
2 Documents in Project
Summary
SCH Number
2012122027
Lead Agency
City of Santa Rosa
Document Title
Administration Drive Sewer Improvements
Document Type
NOD - Notice of Determination
Received
Posted
7/17/2013
Present Land Use
The majority of the project area is designated for Public/Institutional use as part of the County Administration Center.
Document Description
The project will abandon in place an approximately 1500-foot long, 15-inch diameter sewer main spanning approximately 925 linear feet of Paulin Creek. Most work will be completed within the County road right of way but the abandonment process will impact the riparian zone of Paulin Creek. As part of the sewer line abandonment process, the City will need to abandon six manholes located above the ordinary high water mark but within the riparian zone. The abandonment process will require excavation of 8-foot diameter pits approximately 4.5-foot deep at each of the manholes using a mini-excavator or similar equipment. This amount to approximately 300 square feet of temporary disturbance to the riparian area. All disturbed areas will be refilled with soil, compacted, and revegetated. The abandoned pipe will be filled with sand slurry.
Contact Information
Name
Adam McKannay
Agency Name
California Department of Fish and Wildlife
Contact Types
Lead/Public Agency
Phone
Location
Cities
Santa Rosa
Counties
Sonoma
Cross Streets
Fiscal Drive and County Center Drive
Zip
95403
Parcel #
180030007; 180030008
Railways
SMART
Schools
Steele Lane ES
Waterways
Paulin Creek
Notice of Determination
Approving Agency
Fish and Wildlife
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A